Project Description
FALL CREEK REGULATING OUTLET
Project Details
At the Fall Creek Regulating Outlet structure, BCI is replacing four 6ft x 12ft 12,000lb sluice gates and rehabilitating their associated actuators. Each hydraulic actuator must be drained, be disassembled prior to transport down into a 100 ft access gallery, then moved up the gallery to the access hatch. The hydraulic actuator jug is then sent to a fab shop where it is inspected and rehabilitated. While the hydraulic actuator is being rehabbed the existing gate is removed and recycled. New gates are being fabricated by G&G Steel and are installed prior to the installation of the refurbished hydraulic actuator.
Specifications
CUSTOMER NAME
LOCATION
Lane County, Oregon