Project Description
Intake Gate and Bulkhead Replacement at Fort Randall Dam
Project Details
BCI was the prime contractor for this project. The project at Fort Randall Dam in Pickstown, South Dakota consisted of fabrication and installation of 6 new intake gates, fabrication and installation of one new daft tube bulkhead, removal and disposal of one existing draft tube bulkhead, and fabrication and supply of 2 spare roller chains.
Upon completion of the project, BCI will have
- Installed new intake gates
- Installed one new draft tube bulkhead
- Removed one existing draft tube bulkhead
- Designed custom rigging to upright the intake gates from horizontal to vertical for installation by a mobile crane
Specifications
CUSTOMER NAME
LOCATION
Fort Randall Dam, South Dakota